Replaced timber piles with 55 to 68m long steel pipes and installed headstocks to support existing deck structure. Emergency propping and temporary truss supports installed to secure the ship loader as a result of continuous seismic events. Anchor piles with steel tiebacks were installed to secure the new structure and prevent it from moving into the harbour.
The entire wharf deck was removed and reinstated, re-levelled timber headstocks with concrete and reinstated precast wharf deck sections. New concrete slabs around coal gallery, concrete heavy loading access ramp, kerbs and walkways.